August 22, 2004 - Building 8th cable bundle (east) and preparing for
building the 9th bundle (west)
Overview of the approaches and bridge
Note the cable rig platform at each anchor: East work has partially
built the cable bundle, west work is just at the point to moving
the cable rigging platform into position
West platform:
Nothing but the anchor at this point and placing
the cabling rig into position
East platform: Partially completed bundle: note cable ends extending
out the attachment plate in the lower left