Changing the face of Charleston:
Building of the Arthur Ravenel Jr. Bridge
Frank's Home Page
Karpeles Museum display's my story of Building the Ravenel Bridge:
Oct 17, 2007 - ? (Permanent Exhibit)
Archive of building stories
Exploring digital sketches
Unbuilding the Grace and Pearman Bridges
Visit our Photo Essays
Click for all web page building segments
I enjoy hearing from you. If you have comments and suggestions, write me.

Highlights
As seen from the Aquarium
East Bay on ramp
The Last Shark Fin
Closing the main span gap
Paving the bridge
The last stay cable
Opening Events
Engineering Challenges
Stories of Bridge Folks
Erecting Steel
Building Bridge Blog

May 21, 2005:What a difference one night makes.

Early this morning, it was a bit chilly and cloudy. Here is a view looking east from the western end of the bridge. To the right is the last segment to be paved - about 50 feet long.

Walking from west to east, I first encountered the paved segment that was curing yesterday. Hmmm - something happened over night.

Yesterday, you noted (because your curious eyes were enabled - weren't they?) that the Bidwell paving machine was parked near the 9th stay cable anchor. Here you see that it has moved a bit east and is now parked near the 5th stay cable anchor. Sometime during the night, some paving action happened. Also the portable lights have been moved east a distance of about about 4 anchors.

Here the new pavement from last night is curing and if you count the anchors on the left - there are eight - close enought for highway work. Isn't mathematics wonderful? Also the wet burlap that was covering yesterday's segment has been removed and neatly folded.