Paving the Main and Back spans
April 6, 2005
Staring to pave the outside south lane. Note the driver - ready to go
The outside north lane is paved up to the main pylon
March 22, 2005
See all the folks milling around - they are getting organized
March 19, 2005
Just getting started
April 11, 2005
Paving the outer southern lane
April 23, 2005
Looking east and going down hill to Mt. Pleasant
Looking east. Note the channel for the east-west traffic barrier in the
center
April 30, 2005
Paving
Paving continues, albeit at a slow pace due to weather delays. Here are
a couple of photos to give some idea of the scale and progress.
Looking west at the Bidwell machine that spans the inner north lane.
Looking east at the nothern outer and inner lanes.
Paving the southern lanes
Looking west. You can see the rails bounding the inner southern lane
that the Bidwell machine rides on
Here is the outer southern lane, about 25% complete
May 7, 2005: Paving
The paving of the west back span is mostly complete. Here you can see
the rebar outlining the traffic barrier
Looking west down the main span - continuing paving the north outside lane
Drilling holes to set the traffic barrier rebar
May 14, 2005: Paving
The inside east-bound and west-bound lanes are complete and the rebar
that outlines the separation barrier is in place.
The west backspan. Both west-bound lanes are paved as is the
inside east-bound lane - looking east.
The main span looking east.
The east back span looking east.
There is about a 100' segment of the outside west-bound lane to be paved.
The last west-bound segment to be paved
May 20, 2005: More paving painting and stuff
The north and two inner lanes are complete. Only
the south lane remains and it is about 60% complete.
Looking east - only the south lane is incomplete - a short segment at the
end of the west back span and from the east pylon to the end of the east
back span.
The last north segment is complete
The last west main span segment is about 60% complete
The newest south outside segment is curing
And the next south outside segment is being prepared. Note that the Bidwell
machine and portable lights are parked near the 10th stay cable anchor
Now the extra stuff
Looking west as a storm approaches.
You can see that we are nearing the end - preparing for painting lane
markers
and where there are lines, there are line men
Surface preparation and painting is in full swing
The bicycle fence is rapidly becoming reality
A view of the main span and bicycle fence
Teathered and building
Looking west (left) and looking east (right)
May 21, 2005:What a difference one night makes.
Early this morning, it was a bit chilly and cloudy. Here is a view looking
east from the western end of the bridge. To the right is the last segment
to be paved - about 50 feet long.
Walking from west to east, I first encountered the paved segment that
was curing yesterday. Hmmm - something happened over night.
Yesterday, you noted (because your curious eyes were enabled - weren't they?)
that the Bidwell paving machine was parked
near the 9th stay cable anchor. Here you see that it has moved a bit east and
is now parked near the 5th stay cable anchor. Sometime during the night,
some paving action happened. Also the portable lights have been moved east
a distance of about about 4 anchors.
Here the new pavement from last night is curing and if you count the
anchors on the left - there are eight - close enought for highway work.
Isn't mathematics wonderful? Also the wet burlap that was covering
yesterday's segment has been removed and neatly folded.
May 22, 2005
Paving of the south outside lane is almost complete
Sometimes I just get lucky, possibly because I simply cannot sit still.
Just like a high temperature chemical reaction, I am often bouncing around
exploring new ideas. As a kid, I would surely have been
diagnosed with ADD. So today, I bounced up to the bridge and another big
surprise was waiting for me - more paving since yesterday.
So, Friday's, Saturday's and
today's visit yielded big time progress with paving the outside south lane.
Here is a summary of progress since Friday - A lucky view from above
New pavement curing from last (Saturday) night. Note the position of the
5th cable-stay anchor and scroll down to yesterday's (Saturday's) photos
and compare with the launching position of the Bidwell paving machine.
The Bidwell paving machine is in the launching position for the next segment
Cleaning the next segment
I thought I would try to catch the paving this evening. The moon was
full and here is the west pylon bathed in moonlight.
The Bidwell paving machine and the cement mixer were in their
launching positions. The mixer truck is special and can add multiple
components to the resultant concrete.
This is the mixer that mixes the aggregate, sand, cement, latex and water. Each
component is measured (by volume) and dropped onto a src="https://s3.amazonaws.com/s3.ravenelbridge.net/small conveyor belt near
the back of the truck where it is rapidly mixed. The
Styrafan latex 1186 is manufactured by BASF and adds
flexibility and durability to the road surface.
The BAST article describes the paving process better than I can:
"Cleco employed a straightforward process to install the latex-modified
concrete bridge deck overlay. Modified Concrete Suppliers, LLC, Indianapolis,
Ind., their latex concrete supply contractor for this project, used specially
designed trucks equipped with computerized component metering and augers to
mix the Styrofan 1186 latex, cement, sand, aggregate and water on site for
application to the bridge deck surface. Following application to the bridge
deck, Cleco employees used a Bid-Well finishing machine to spread and trowel
the overlay to achieve thickness and surface smoothness specifications. Once
installation of a section was completed, wet burlap was applied to the surface
of the overlay, covered with polyethylene sheeting, and allowed to moist cure
for 24 hours. This step controlled the rate of water evaporation from the
overlay. After two days of dry cure, the surface was ready for use."
But there was a small problem. In order for the concrete to
cure properly, i.e. no cracks, the evaporation rate must be
below a limit which is determined by the temperature, humidity and wind
velociy. Here Derek (left) has an instrument that measures all this. Here
he and JW (right), from Cleco, are checking the wind
conditions. In general, I am told, winds above 10 mph are problematic.
After a bit of waiting - well it seems that tonight is not the
night for paving ...
A digital sketch of night paving
May 25, 2005
Paving is finished - and what a sunset!
I spent the day at the Savannah River Research Center and did not get
back to Charleston until about 6pm. I got to the bridge about 8pm thinking
I'll look and surely they will not start paving before 10pm.
I got there and guess what? - they had not only started they have almost
finished. So here is the end of the paving story.
First - your typical Charleston sunset - simply fantastic
And the 50 foot (more or less) last segment - looking east
The last segment looking west
The tired Bidwell paving machine
Remaining was a src="https://s3.amazonaws.com/s3.ravenelbridge.net/small gutter to be paved
Here is the entire team waiting for everything to be in their respective
launching positions. The man on the left is operating the mixing machine
while the guys on the right are waiting for the mixed concrete to slide down
the delivery trough.
Doing the finish work and the sunset.
As the mixing truck drives into the sunset, here is a final view of the
entire paving ensemble - a mixer, the team and the sunset.
This work is licensed under a Creative Commons License.
Attribution: C. Frank Starmer from http://ravenelbridge.net
_