August 29, 2004
No early morning bike ride today - maybe later, if Gaston behaves.
Frances is in the lower right - next week's challenge.
Main Span
West Pylon 9th anchor extended to the west and 9th cable bundle completed
on the channel side. Note Hurricane cable anchors under the left end of the deck
|
East Pylon 8th cable bundled completed on the channel side.
|
|
|
August 29, 2004 7pm: Guess what? We have a bit of sun BUT,
over the past few hours, Hermine has suddenly appeared.
Main Span
West Pylon
|
East Pylon
|
|
|
August 29, 2004 3 of the four deck cranes have their booms lowered,
but all looks ok
West approach: Note that poking up from the river under
the end of the west (left) deck are the
anchors for the next set of hurricane cables - just in time.
East approach
West approach - About 4 hours later (7pm)
East approach
This work is licensed under a Creative Commons License.
Attribution: C. Frank Starmer from http://ravenelbridge.net
_