October 22, 2004: Final group of three anchors added to the east pier
Main Span
West Pylon
|
East Pylon
|
|
|
October 22, 2004:
West approach: Completing 12th cable bundles
East approach: Addition of the 12th anchors
West Approach: Completed the 12th cable bundles
|
East Approach: Completed the installation of the east pier triple anchor beam
|
|
|